We’re delighted to report that the latest stage of the implementation of the UK’s first wastewater micropollutant removal plant at Frankton, Warwickshire, has been completed.
The civil engineering work was finalised in July as planned, allowing for the installation of three vessels through which the effluent will flow. The next stage will be to install the Tertiary Solids Removal (TSR) filtration system, being provided by Severn Trent Water, followed by our containerised ozone water treatment systems. In the meantime, we will be creating the interconnecting pipework.
This is an exciting stage in the project, and as the site begins to take further shape, we’ll keep you posted.